Supplier Risk
Lead time and reliability recomputed from 220 historical purchase orders (order date to actual receipt), compared against the promised delivery date. Master-data lead times were broadly accurate; on-time performance was materially worse than the supplier master claims for every supplier.
Average lead time by supplier
Bars show actual mean order-to-receipt days; label shows lead-time standard deviation.
Lead time vs OTIF reliability
Bottom-right quadrant is the danger zone: slow and unreliable. Bubble size = lead-time variability.
Supplier scorecard
Master data vs measured performance
| Supplier | Category | POs | Stated LT | Actual LT | σ LT | P95 LT | Stated OTIF | Actual OTIF |
|---|---|---|---|---|---|---|---|---|
| Trackline ManufacturingHighest risk | Undercarriage | 43 | 35d | 33.4d | 10d | 50d | 82% | 65.1% |
| Meridian Hydraulics Ltd. | Hydraulic Components | 48 | 21d | 20.4d | 3.7d | 26d | 91% | 58.3% |
| Circuit & Cab Electronics | Electrical & Cabin | 50 | 28d | 26d | 5.4d | 35d | 88% | 66% |
| Ironclad GET Works | Ground Engaging Tools | 41 | 14d | 13.7d | 1.7d | 16d | 97% | 68.3% |
| Vantage Engine Systems | Engine & Powertrain | 38 | 18d | 17.3d | 2.4d | 21d | 95% | 73.7% |
Why Trackline Manufacturing is the priority
Trackline delivers Undercarriage in 33.4 days on average with a 10-day standard deviation and a P95 of 50 days — roughly twice the network mean and more than triple the variability of Ironclad GET Works. Because safety stock scales with lead-time variability multiplied by mean demand, that single supplier drives the largest buffer requirement in the portfolio.
Trackline is also the only supplier whose unreliability has already cost sales: the weeks 40-45 disruption emptied both Asia Pacific DCs and censored six weeks of demand history. Single-sourcing an entire category from the slowest and least reliable vendor in Asia Pacific — where two of four DCs sit — concentrates the risk exactly where the volume is.
Circuit & Cab Electronics (26d, σ 5.4d) is a secondary watch item; Ironclad GET Works and Vantage Engine Systems are performing to expectation.
Recommended actions
- 1Buffer Undercarriage to the P95 lead time
Plan Trackline items against 50 days rather than the 35-day master value, and raise the Undercarriage service level to 97.5% at the Asia Pacific DCs. Roughly a 40% increase in Undercarriage safety stock.
- 2Open a secondary source for Track Shoe and Track Chain
Qualify a second Undercarriage vendor for the two highest-volume SKUs and target a 70/30 split. Dual sourcing beats buffering here: the buffer cost of a 33-day, σ 10-day lead time exceeds any realistic unit-price premium.
- 3Correct the supplier master and put OTIF on the QBR
Measured on-time-in-full is 12-31 points below the stated figures for every supplier, so planning parameters derived from the master are optimistic. Replace them with rolling 12-month actuals and review monthly.